CS605
|
The Level 1 Of Cmm Is Known As__________
|
Managed
|
Initial
|
Defined
|
Repeatable
|
B
|
CS605
|
Which One Of The Following Does Not Belong To A Strategy For Dealing With Risk?
|
Risk Avoidance
|
Security Risk Assessment
|
Risk Monitoring
|
Risk Management And Contingency Planning
|
B
|
CS605
|
Metrics To Assess The Quality Of The Analysis Models And The Corresponding Software Specification Were Proposed ............
|
In 1993- 1999
|
Ricado In 1993
|
Davis In 1990
|
Davis In 1993
|
D
|
CS605
|
Se Is The Set Or The Combination Of Processes And Tools To Develop Software
|
True
|
False
|
Na
|
Na
|
A
|
CS605
|
In The Software Development Life Cycle Soon The Defect Is Detected Will Results In
|
Increase In Cost Of Software
|
Decrease In Software Cost
|
Both A And B Are Correct
|
None Of These
|
B
|
CS605
|
During The Construction Of Software Defects Can Be Prevented From Being Injected In Software With The Help Of
|
Proper Education And Training Of Software Engineers
|
Use Of Formal Methods
|
Use Of Appropriate Tools For Testing
|
All Of The Given Option Are Correct
|
A
|
CS605
|
Main Characteristic Of __________ Model Is Risk Analysis And Management
|
Waterfall
|
Rad
|
Spiral
|
Incremental
|
C
|
CS605
|
Every Task Has Some__________And Every Deliverable Should Be Delivered At Particular__________
|
Deliverable Milestone
|
Milestone Deliverable
|
Deliverable User
|
Milestone User
|
A
|
CS605
|
__________ Model Is Developed Keeping In Mind The Element Of Risk In The Development Of Software
|
Spiral
|
Rad
|
Incremental
|
Synchronize And Stabilize
|
A
|
CS605
|
___________Give You A Better Insight Into The State Of The Process Or Product
|
Metrics Page
|
Efficiency
|
Reliability
|
Usability
|
A
|
CS605
|
The Rmmm Plan Assists The Project Team In Developing Strategy For Dealing With Risk. In This Context An Effective Strategy Must Consider
|
Risk Avoidance
|
Risk Monitoring
|
Risk Management And Contingency Plan
|
All Of The Given Choices
|
D
|
CS605
|
Coper Jones Divided The Software Activities Into__________Different Categories
|
24
|
25
|
26
|
27
|
B
|
CS605
|
According To Fred Brook Software Is Like A…………….
|
Applications
|
Packags
|
Giant
|
None Of These
|
C
|
CS605
|
In __________ Model Product Is Constructed Without Specification Or Any Attempt At Design
|
Build & Fix Model
|
Waterfall Model
|
Rad
|
None Of These
|
A
|
CS605
|
Cmm Is Developed By Sei To Judge The__________Of An Organization
|
Process Maturity Level
|
Process Maturity Model
|
Process Maturity Techniques
|
None Of These
|
A
|
CS605
|
__________Is Data That Influences An Elementary Process Of The Application
|
Elementary Process
|
External Query
|
External Output
|
Control Information
|
D
|
CS605
|
We Can Include Following Type Of Data In The Database For Creating Matrix Against Each Project Except
|
Name Of Project
|
Size Of Project
|
Company’S Ceo Name
|
Cost Of Project
|
C
|
CS605
|
Effective Software Project Management Focuses On The Four P’S: These Are
|
People Product Process Problem
|
People Passion Process Project
|
People Product Process Project
|
People Passion Planning Project
|
C
|
CS605
|
In __________ Level Of Cmm Detailed Measures For Software Process And Product Quality Are Controlled
|
Level 1
|
Level 2
|
Level 3
|
Level 4
|
D
|
CS605
|
Water Fall Model Is A Document Driven Model
|
True
|
False
|
Na
|
Na
|
A
|