Code Question Option A Option B Option C Option D Answer
CS605
Effective Software Project Management Focuses On The Four P’S: These Are
People Product Process Problem
People Product Process Project
People Passion Process Project
People Passion Planning Project
B
CS605
Effective Software Project Management Focuses On The Four P’S: These Are
People Product Process Problem
People Passion Process Project
People Product Process Project
People Passion Planning Project
C
CS605
Effort Required To Test A Program To Ensure That It Performs Its Intended Function __________
Testability
Bug Fixing
Debugging
Security
A
CS605
Empirical Models Are Statistical Models And Are Based Upon Historic Data
True
False
Na
Na
A
CS605
Every Node Signifies __________ Version Of A Release
One
Two
Three
Four
B
CS605
Every Task Has Some__________And Every Deliverable Should Be Delivered At Particular__________
Deliverable Milestone
Milestone Deliverable
Deliverable User
Milestone User
A
CS605
Every Task Should Be Assigned To A Specific Team -------------
Member
Manager
Organizer
None Of The Given
A
CS605
Extent To Which Access To Software Or Data By Unauthorized Persons Can Be Controlled And Called ……….…
None Of Given
Efficiency
Reliability
Integrity
D
CS605
Fast Is The Abbreviation Of
Facilitated Application Specification Technology
Facilitated Application Specification Technique
Facilitated Application Specialization Technique
None Of The Above Option
B
CS605
Following Are Effective Guidelines For Review Except
We Need To Review The Product Not The Producer
Be Sensitive To Personal Egos
Errors Should Be Pointed Out Gently
Tone Should Be High And Strict
D
CS605
Following Are The Benefits Of Conducting Review Except
Help In Finding The Size Of The Project
Helps In Verifying The Quality Of Product
Help In Identifying Where Improvement Is Required
Helps In Identifying The Bugs In The Work Product
D
CS605
Following Are The Components Of A Legacy System Except
Business Processes
System Hardware
Marketing
Application Software
C
CS605
Following Are The Reasons For Project Failure Except
Requirements Are Not Clear
The Name Of The Software
Processes Have Not Been Established In The Organization
Un-Realistic Deadline
B
CS605
Following Factors Should Be Considered While Assessing The Legacy System Except
Age Of Hardware And Software
Failure Rate
Support Requirement
Name Of The Client
D
CS605
Following Is Not The Golden Principle Of Business Process Re-Engineering
Organize Around Outcomes Not Tasks
Have Those Who Use The Output Of The Process Perform The Process
Do Not Treat Geographically Information As Centralized
Incorporate Information Processing Work Into The Real Work That Produces The Raw Information
C
CS605
For __________ Level Of Cmm No Kpas Are Defined
Level 1
Level 2
Level 4
Level 5
A
CS605
From The Following Listed Software Development Model Which One Is An Object Oriented Model
Classical Life Cycle Model
Fountain Model
Spiral Model
Waterfall Model
A
CS605
Function Point Analysis Is Helpful In Calculating The Size Of The Software For __________
Both Client And Software Organization
Software Organization
Client
User
D
CS605
Function/Test Matrix Is A Type Of
Interim Test Report
Final Test Report
Project Status Report
Management Report
C
CS605
------------------Give You A Better Insight Into The State Of The Process Or Product
Metrics
Reliability
Efficiency
Usability
A