Code Question Option A Option B Option C Option D Answer
CS605 Effective Software Project Management Focuses On The Four P’S: These Are People Product Process Problem People Product Process Project People Passion Process Project People Passion Planning Project B
CS605 Effective Software Project Management Focuses On The Four P’S: These Are People Product Process Problem People Passion Process Project People Product Process Project People Passion Planning Project C
CS605 Effort Required To Test A Program To Ensure That It Performs Its Intended Function __________ Testability Bug Fixing Debugging Security A
CS605 Empirical Models Are Statistical Models And Are Based Upon Historic Data True False Na Na A
CS605 Every Node Signifies __________ Version Of A Release One Two Three Four B
CS605 Every Task Has Some__________And Every Deliverable Should Be Delivered At Particular__________ Deliverable Milestone Milestone Deliverable Deliverable User Milestone User A
CS605 Every Task Should Be Assigned To A Specific Team ------------- Member Manager Organizer None Of The Given A
CS605 Extent To Which Access To Software Or Data By Unauthorized Persons Can Be Controlled And Called ……….… None Of Given Efficiency Reliability Integrity D
CS605 Fast Is The Abbreviation Of Facilitated Application Specification Technology Facilitated Application Specification Technique Facilitated Application Specialization Technique None Of The Above Option B
CS605 Following Are Effective Guidelines For Review Except We Need To Review The Product Not The Producer Be Sensitive To Personal Egos Errors Should Be Pointed Out Gently Tone Should Be High And Strict D
CS605 Following Are The Benefits Of Conducting Review Except Help In Finding The Size Of The Project Helps In Verifying The Quality Of Product Help In Identifying Where Improvement Is Required Helps In Identifying The Bugs In The Work Product D
CS605 Following Are The Components Of A Legacy System Except Business Processes System Hardware Marketing Application Software C
CS605 Following Are The Reasons For Project Failure Except Requirements Are Not Clear The Name Of The Software Processes Have Not Been Established In The Organization Un-Realistic Deadline B
CS605 Following Factors Should Be Considered While Assessing The Legacy System Except Age Of Hardware And Software Failure Rate Support Requirement Name Of The Client D
CS605 Following Is Not The Golden Principle Of Business Process Re-Engineering Organize Around Outcomes Not Tasks Have Those Who Use The Output Of The Process Perform The Process Do Not Treat Geographically Information As Centralized Incorporate Information Processing Work Into The Real Work That Produces The Raw Information C
CS605 For __________ Level Of Cmm No Kpas Are Defined Level 1 Level 2 Level 4 Level 5 A
CS605 From The Following Listed Software Development Model Which One Is An Object Oriented Model Classical Life Cycle Model Fountain Model Spiral Model Waterfall Model A
CS605 Function Point Analysis Is Helpful In Calculating The Size Of The Software For __________ Both Client And Software Organization Software Organization Client User D
CS605 Function/Test Matrix Is A Type Of Interim Test Report Final Test Report Project Status Report Management Report C
CS605 ------------------Give You A Better Insight Into The State Of The Process Or Product Metrics Reliability Efficiency Usability A